Work resumes on Katsina-Ala–Takum Road after two-year suspension over insecurity

Mr Igban said the company had to stop work due to numerous security challenges along the road corridor.

• February 16, 2026
Katsina-Ala –Takum Road
Katsina-Ala –Takum Road

Work has resumed on the 78.62-kilometre Katsina-Ala-Takum Road after a two-year delay due to numerous security challenges along the road corridor.

James Igba, project coordinator at Gerawa Global Engineering Nigeria Limited, the contractor handling the road reconstruction, said the company took over the site on November 27, 2023.

Mr Igban, who received officials of the Federal Ministry of Works (FMW) on an assessment tour of road infrastructure, told the team, led by its spokesperson, Mohammed Abdullahi, that the project was to be completed in December 2025.

“We have applied for an 18-month extension, and we are waiting for approval from the ministry.

“We are back on site, preparing our earthwork ready for the stone base. We will soon start laying the stone base and binder works.

“We are also going to continue with hydraulic works and the extension of culverts, as well as drainage.

“We want to assure the ministry and all the stakeholders that we are fully back on-site and that the challenges we had have been surmounted,” he stated.

Mukaila Danladi, the Benue controller of works at the Federal Ministry of Works, said the contractor had reached a binder level of 2.5 kilometres.

“From 2.5 kilometres to 12 kilometres, they have achieved sub-base level and are ready to receive the base course.

“The Benue government’s ban on blasting of rocks also affected the pace of the contract apart from the security challenges,” he stated.

Mr Abdullahi, the FMW team lead, said the tour was to gauge the perception of the federal government’s interventions in road infrastructure.

He said the enhancement of road infrastructure and transportation is one of eight pillars of the administration’s Renewed Hope Agenda.

The director added that the tour was also to inaugurate completed emergency projects.

“This administration inherited a total of 3,064 roads at inception on May 29, 2023, some of which were abandoned because of a paucity of funds.

“The debt hangover of the project was up to N30 trillion, and the government completed the projects and rehabilitated the failed portions of roads,” he said.

Ukeyima Manger, immediate past chairman of the Nigerian Society of Engineers, Benue chapter, lauded the federal government for awarding the contract to ease the suffering of road users.

(NAN)

We have recently deactivated our website's comment provider in favour of other channels of distribution and commentary. We encourage you to join the conversation on our stories via our Facebook, Twitter and other social media pages.

More from Peoples Gazette

farmers

Agriculture

FG tasks ECOWAS on leveraging financing strategies for agroecology

The federal government has urged stakeholders in the agriculture and finance sectors in the West Africa region to leverage financing strategies to enhance agroecology practices

Katsina State

Politics

Katsina youths pledge to deliver over 2 million votes to Atiku

“Katsina State is Atiku’s political base because it is his second home.”

Bankole Adeoye

Africa

AU commissioner calls for permanent ceasefire in Sudan, DR Congo

Mr Adeoye said the situation in Sudan is “the worst humanitarian crisis globally” and that the conflict, which began in April 2023, remains “virtually unreported.”

President Bola Tinubu

States

Tinubu arrives Yola to inaugurate key projects

The projects include model schools built across the 21 local government areas of the state.

Police officer

States

Police foil planned bandit attack in Oyo community, kill two

Mr Ayanlade said the rest of the suspected bandits, after engaging in a gun duel with the operatives, escaped with bullet wounds.

Nigerian Senate

Agriculture

Budget: Senate wants North-Central commission to prioritise investments in agriculture

The lawmaker, however, said the committee was dissatisfied with the implementation of the capital component of the 2025 budget.

Education

Bauchi gov’s wife distributes 10,000 sanitary pads to schoolgirls

Mrs Mohammed said the intervention was under the Renewed Hope Initiative (RHI) of the First Lady, Oluremi Tinubu.

Enugu State police

States

Police arrest chief priest, three others over kidnap, murder of Cameroonians

Mr Ikenga said the suspects were arrested during an operation in Nando, Anambra East Local Government Area (LGA), on Friday.